Colloide
 
Waste water treatment plant  -  ARDEE
Previous 
 Next
Project outline:
The existing water treatment works, consisting of 2no. clarifier tanks and 2no. sand filters were upgraded by fitting lamella plates into the two tanks. The overall demand on the works is approximately 140m3/hr.
Project description:
Project Detail

Colloide provided Louth County Council with the following equipment as part of the overall project;
- Lamella plates
- Framework for lamella plates
- New sludge cones and Pipework
- Control system for desludging
- Removal of existing sludge hoppers
- New distribution pipe for incoming water
- Refurbishment of existing launder system

Further information
Due to the demand for water from the existing works, plant downtime had to be minimized.

As part of the contract, Colloide provided a temporary clarifier when the existing clarifiers were being refurbished.
 