Bunhill District Heating Project Update

Colloide began the construction of the Bunhill ll Energy Centre back in December 2016. The pictures below highlights the progress of this phase of the works to date.

December 2016 – Prep works begins on site for foundations.

Bunhill District Heating Project
Bunhill District Heating Project

 

 

 

 

 

 

 

 

 

 

January 2017 – Foundation works begin on site

Bunhill Energy Centre - Foundations
Bunhill Energy Centre – Foundations

 

 

 

 

 

 

 

 

 

 

March 2017 – Vent Shaft works takes place.

Bunhill Energy Centre - Vent Shaft works
Bunhill Energy Centre – Vent Shaft works

 

 

 

 

 

 

 

 

 

 

September 2017 – The new ventilation shaft is near competition

Bunhill Energy Centre - Vent Shaft works completed
Bunhill Energy Centre – Vent Shaft works completed

 

 

 

 

 

 

 

 

 

 

 

Bunhill Energy Centre Tour

Local residents had the opportunity to visit Bunhill phase l energy centre earlier this month. These visitors experienced first-hand how heat networks operate and they also received information on the benefits that the network brings to local communities.  Colloide are currently completing the construction works on Phase 2 of the project.

Bunhill Energy Centre Tour - District Heating
Bunhill Energy Centre Tour – District Heating

 

 

 

 

 

 

 

 

 

Did you know?

Bunhill tour - fun fact
Bunhill tour – fun fact

 

 

 

 

 

 

 

 

 

 

 

Image credits: Islington Energy

 

Bunhill Energy Centre Tour - District Heating